BAGUIO CITY, Dec. 16 -- The Baguio Water District (BWD) has completed a PHP24.2 million pipeline project, installing 7,505 meters of new pipes across the city to improve service and reduce water loss.
General Manager Engr. Salvador Royeca said Tuesday the 2025 project included 28 major works: 11 repiping projects to replace old lines, 10 extension lines to reach new areas, four new transmission lines, and three upsizing projects for high-demand zones.
"The repiping and new piping project underscores the BWD's commitment to expand access, reduce losses, and prepare for the increasing demand for water," Royeca said.
The upgrades address current needs and anticipated population growth for the district's 51,004 active connections. Additional...