Manila, Nov. 25 -- A six-hour yellow alert has been raised over the Visayas grid from 3 p.m. to 9 p.m. Wednesday due to outages at several power plants, the National Grid Corporation of the Philippines (NGCP) said.

In an advisory, the grid operator said the Visayas grid has an available capacity of around 2,609 megawatts (MW), leaving a thin reserve margin against the contingency requirement, as peak demand is projected to reach 2,529 MW.

It traced the limited capacity primarily to the unplanned outage of Unit 2 of the Therma Visayas Inc. (TVI) and derated capacity of TVI 1, the scheduled outage of the Palm Concepcion Power Corporation (PCPC) and the KEPCO SPC Power Corporation, and the derated capacity of the Leyte-A, a geothermal powe...