GANGTOK, India, April 27 -- Sikkim High Court issued the following judgment/order on March 24:
1. Heard W.A. No.02 of 2026 and W.A. No.03 of 2026.
2. Both matters came up for admission. We propose to dispose of both these matters together.
3. The Respondents have also entered appearance.
4. We have the advantage of hearing learned Counsel for the Appellant as well as learned Counsel for the Respondents.
5. These matters arise in these appeals from two separate writ petitions filed by landholders whose houses are alleged to have suffered damage consequent upon the works undertaken by the appellant on behalf of the Railways.
6. The main issue is with regard to the sustainability of the interim orders dated 12.12.2025 passed by the ...