India, Aug. 5 -- The Government of India has issued a release:

The Government has announced an ambitious Nuclear Energy Mission for Viksit Bharat with a target of reaching a nuclear power capacity of 100 GW by 2047. Nuclear Power Projects are having a Project/ Construction period of 10-12 years. No specific Nuclear Power Projects have been sanctioned after the Middle East conflict.

Nuclear Power Projects under Construction/ Commissioning

Location & State

Project

Capacity

Expected Completion Date/

Indigeneous/

Rawatbhata, Rajasthan

RAPP-8

1 X 700

Unit-8 is in advanced stage of commissioning (expected to

Indigeneous

Gorakhpur, Haryana

GHAVP

2 X 700

Completion of construction and commissioning is expected to be completed in abo...