India, Dec. 28 -- The Government of India has issued a release:
ICF Chennai: 1,659 coaches
MCF Raebareli: 1,234 coaches
RCF Kapurthala: 1,331 coaches
Physical Progress: Overall physical progress of 55.63% has been achieved as on 30th November 2025.
Financial Progress: Overall financial progress of 69.62% with an expenditure of Rs. 85,801/- crore has been achieved as on 30th November 2025.
Important Civil Engineering Parameters: Total 412 km of foundation, 405 km of Piers, 344 km of Girder Casting and 330 km of Girder launching completed till 30th November 2025.
Vijapur-Ambliyasan Gauge Conversion
Domingarh-Gorakhpur-Gorakhpur Cantt.-Kusumhi - 3rd running line and Gorakhpur-Nakaha Jungle Doubling
Bahraich-Nanpara-Nepal Ganj Gauge Co...