GUWAHATI, India, Sept. 12 -- Gauhati High Court issued the following order on Aug. 12:
1. Heard Mr. S. Choudhury, the learned Senior Counsel assisted by Mr. T. Bose, the learned counsel appearing on behalf of the petitioner. Mr. D. Saikia, the learned Senior Counsel assisted by Mr. P. Nayak, the learned counsel appears on behalf of the respondents.
2. The petitioner herein has approached this Court challenging the termination of the contract bearing No. 6119345/ CDG3526P24/DRLG/24 vide the termination notice dated 09.06.2025 as well as the subsequent communication dated 18.06.2025, whereby the petitioner has been asked to vacate the drilling site with immediate effect.
MATERIAL FACTS ON THE BASIS OF PLEADING
3. The case of the petiti...