Project Name

Rehabilitation and upgradation of Ghoti - Trimbak (Mokhada) - Jawhar - Manor - Palghar section of NH-160A to 2 Lane /4 Lane with paved shoulder configuration and in the state of Maharashtra on Engineering, Procurement and Construction (EPC) Mode.

Corridor

Sinnar to Palghar NH 160A

Length (km)

154.635

Total Civil Cost (Rs Cr.)

2594.49

Land Acquisition Cost (Rs Cr.)

725.89

Total Capital Cost (Rs Cr.)

3320.38

Mode

Engineering, Procurement and Construction (EPC) Mode

Major Roads Connected

Expressways: Delhi-Mumbai Expressway (NE-4) and Mumbai-Nagpur Samruddhi Mahamarg

Economic / Social / Transport Nodes Connected