Ambedkar memorial delayed by 2 more yrs
MUMBAI, Nov. 22 -- The grand memorial to Dr B R Ambedkar at Indu Mills, Dadar, will miss its December 6 deadline-the Mahaparinirvan Diwas-and is likely to take another two years to complete.
While the complex-featuring a 1,000-seater auditorium, library, research centre, and exhibition halls-is nearly ready, work on the 350-foot Statue of Equality atop a 100-foot pedestal is delayed. Having missed four deadlines already, including December 2026, the project's executing agency, MMRDA, recently issued a show-cause notice to contractor Shapoorji Pallonji, Group threatening termination over the delays.
The project was awarded to Shapoorji Pallonji in February 2018. Its cost has escalated from from Rs.622 crore to an estimated Rs.1,200 crore. P2...