Varanasi, Aug. 26 -- The Varanasi ropeway project is expected to be fully operational by the end of December 2025. The project includes key stations at Varanasi Cantt, Vidyapeeth, Rathyatra, Girijaghar, and Godaulia Chauraha. During an inspection of all stations, divisional commissioner S Rajaligam instructed project director of NHLML, Pooja Mishra, and other officials to complete the work by December 12. A joint traffic plan is to be prepared with the Railway and Public Works Departments. Work at Vidyapeeth and Rathyatra stations must also be finished by September-end. For Girijaghar, roadblocks will be arranged from 9 pm to 9 am starting August 28.Pile work at Godaulia station should be completed soon. The commissioner was unhappy with the slow pace and instructed that a weekly work plan be made and inspected personally. The deadline for the Varanasi Cantt to Rathyatra section is September 30, while the second section, from Godaulia Chauraha to Girijaghar, must be finished by December 12, 2025.htc...