India, Nov. 22 -- Two days after Rohan Bhate, honorary wildlife warden, Satara forest department, raised questions over the statutory clearances obtained for the 1,500 MW Tarali Pumped Storage Project (PSP), the Maharashtra Pollution Control Board (MPCB) on Friday issued a stop-work notice to Adani Renewable Energy One Limited for allegedly undertaking unauthorised excavation and construction activities on two land parcels in Sawarghar village in Satara district.

The notice directs the company to immediately stop ongoing and proposed activities at the two sites, where temporary labour accommodation and material storage facilities are being developed. MPCB said the company had undertaken the work without obtaining permissions from the boa...