New Delhi, Jan. 17 -- The Public Works Department (PWD) has debarred a consultancy firm from participating in its tenders for two years and imposed a penalty of Rs.50 lakh, citing prolonged delays, non-compliance with contractual obligations and cost escalations in the construction of four ICU hospital projects in the Capital. In an order earlier this week, PWD said that the firm had failed to deliver requisite drawings, designs and statutory compliance documents for ICU hospital projects at Shalimar Bagh, Kirari, Chacha Nehru Bal Chikitsalaya and Guru Teg Bahadur Hospital. The project involved new constructions at the first two locations, and expanding ICUs of the operational Bal Chikitsalaya and GTB Hospital. "Long and unexplained delays ...