India, Aug. 25 -- The Gurugram Metropolitan Development Authority (GMDA) is set to complete its fifth unit of water treatment Plant (WTP) at Chandu Budhera by December this year, said officials.

Officials said that the unit, with a capacity of 100 MLD, will become operational by January next year and increase the GMDA's total water treatment capacity to 770 MLD -- 400 MLD at Chandu Budhera and 370 MLD at Basai.

Currently, the GMDA operates four water treatment units at Chandu Budhera, each having 100 MLD capacity, taking the total capacity to 400 MLD.

The court plant was made operational in April this year, which significantly increased water supply in areas such as Gol course abroad, MG road and around Palam Vihar, said officials.

A ...