Can't penalise allottee for delay in construction if possession delayed: HC
Chandigarh, Nov. 21 -- The Punjab and Haryana high court (HC) has held that an allottee can be held responsible for non-construction only if the plot has been made available to her and she fails to raise construction despite having a reasonable opportunity to do so.
"Where possession itself remains undelivered, the mere expiry of the construction period stipulated in the allotment letter would not, by itself, establish a default attributable to the allottee," the bench of justice Suvir Sehgal and justice Rajesh Gaur observed while dismissing an appeal from the Greater Mohali Area Development Authority (GMADA).
According to the judgment, one Harwinder Kaur applied for a residential plot in Mohali and deposited Rs.1.5 lakh towards registr...