4.5km railway drain project sees 19% cost jump in 5 mnths
New Delhi, Nov. 17 -- The project to develop a 4.5km-long tunnel-like drain along the railway lines in northwest Delhi has seen a 19% cost escalation, just five months after the initial cost was decided, senior officials of the irrigation and flood control (I&FC) department said on Monday.
The covered trunk drain is supposed to resolve the drainage problem of four adjoining areas - Kirari, Mundka, Bawana and Nagloi.
The government, in June this year, had estimated the project cost at Rs.200 crore, which was increased to Rs.220.93 crore after the agency which was given the bid proposed a higher estimate, according to an order sanctioning increased allocation dated November 3.
"The irrigation department's work advisory board, comprising the p...