Kathmandu, Sept. 4 -- Why is the Narayanghat-Butwal road important?

It is a major westbound route connecting Kathmandu and the central regions to the western parts of Nepal. Traffic surges during festivals like Dashain and Tihar, making road conditions a key concern for travellers.

When did the highway widening project start, and why was it delayed?

Work began over six years ago in 2019. Multiple factors have caused delays, including construction challenges, monsoon interruptions, and project management issues. The original completion date was July 2022, but it has now been extended to July 2026.

Who is responsible for the project, and what is its cost?

The highway is being widened under a contract awarded to China State Construction...