Mumbai, Oct. 23 -- The scope of work pertains to the supply of Goods for the Balance of System (BOS) for the 650 MW solar power project at Khavda Renewable Energy Park, Gujarat. It includes complete design, engineering, manufacturing, procurement, quality assurance, packing, and delivery of materials at site.

The scope also covers onsite services, including receipt, unloading, storage, handling, installation, testing, and commissioning of free-issue materials, along with associated civil, mechanical, electrical, and structural works required for successful project commissioning.

The said order is worth Rs 1,050 crore and it is expected to be completed within 1 year from receipt of (LOI).