Mumbai, Jan. 29 -- In an exchange filing, the company said the order pertains to the construction of a road over bridge (ROB) featuring a 36.0-metre composite girder, two 24.0-metre composite girders and four 18.75-metre T-beam girders. The project will be executed at railway kilometre 649/11-13, in lieu of LC No. 348 at km 649/13-15, between Sompeta and Baruva railway stations on the main line under the Khurda Road Division.
The total contract value stands at Rs 51,79,91,303.99 and the project is scheduled to be completed within a period of 24 months.
The company further clarified that none of its promoters or members of the promoter group have any interest in the entity awarding the contract. It also stated that the transaction does n...