New Delhi, May 20 -- The Mumbai-Ahmedabad Bullet Train project achieved a major engineering milestone after workers successfully launched a 130-meter-long steel bridge span over Indian Railway tracks near Tralsi village in the Bharuch district of Gujarat. The newly positioned section marks the completion of 230 meters of the steel bridge out of its total 330-meter length.

The bridge crosses the Dedicated Freight Corridor Corporation (DFCC) tracks between the Surat and Vadodara section of the Western Dedicated Freight Corridor.

The structure is a three-span bridge that consists of a 100-meter and 130-meter continuous span, alongside an additional 100-meter simply supported span. The 130-meter section was moved into position on May 16, 20...