India's first bullet train to undergo trials on 50-km stretch in May 2027
New Delhi, Nov. 23 -- India's first bullet train project is expected to enter its trial phase in May 2027, with the 50-km Surat-Bilimora section of the Mumbai-Ahmedabad high-speed rail corridor being prepared for the initial testing, Union Railway Minister Ashwini Vaishnaw said on Monday.
Addressing a media briefing, Vaishnaw said electrification of the stretch had been completed, while signalling-related work was expected to be finished by January 2027.
The overhead electrification system on the elevated section was energised on November 20, covering both tracks. The section operates on a 2x25 kV traction system, with installation work at the Bilimora traction substation also completed.
The minister said the high-speed rail corridor w...