Klungkung, Bali, Oct. 31 -- Bali authorities have suspended construction of a 182-meter glass elevator at the cliff of Kelingking Beach in Nusa Penida, Klungkung District, citing environmental concerns and regulatory violations.
I Made Supartha, head of a special committee on spatial affairs, assets, and permits at the Bali legislature, said the project violated Law No. 26 of 2007 on Spatial Planning.
"The Bali Municipal Police will ensure that no construction activities continue here," Supartha said on Friday.
He noted that the project lacked multiple permits, including those for disaster mitigation and work safety, and failed to incorporate the Bali-style design required under regional regulations.
Bali Municipal Police officer I De...