BALESWAR, Jan. 16 -- A much-hyped flyover under construction near Tamulia level crossing in Baleswar town even after facing time and cost overrun is yet to see the light of the day

The progress of the over bridge with original estimated project of Rs 44 crore is dismal even after a lapse of nearly five years since the foundation stone was laid. The target date for completion of the bridge was September, 2017.

Even having missed the deadline, the department expects that the bridge would be completed by end of January claiming most of the works have been completed.

However, sources besides stating that the main span work of the bridge was not completed said a key factor before making the bridge operational is shifting of the 33-KV line whi...